Traveltimes along Clear Creek and selected tributaries upstream from Golden, Colorado, 1996-97
<p>Increased traffic along mountainous stretches of Interstate Highway 70, U.S. Highway 40, and U.S. Highway 6 in Colorado has resulted in a corresponding…
Public-domain full text preserved in the Mountain Man Mining Library. Original source: pubs.usgs.gov.
usGs science for a changing world TRAVELTIMES ALONG CLEAR CREEK AND SELECTED TRIBUTARIES UPSTREAM FROM GOLDEN, COLORADO, 1996-97 U.S. GEOLOGICAL SURVEY ovo gA DO Grand Colorado Junction *Springs Pueblo ARKANSAS RIVER Water-Resources Investigations Report 98 4151 cooperation with the QE LACKHAWK .U58w no.98-4151
LIBRARY wrp-s-c LIE3 RN I N Bureau of Reclamation Rriarn3tinn Service Centel
Gaylord Printed In U.S.A.
BUREAU OF RECLAMATION DENVER LIBRARY III II lill IIII I III II eio, YAVv'fie Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97 By Sally M. Cuffin U.S. GEOLOGICAL SURVEY Water-Resources Investigations Report 98-4151 Prepared in cooperation with the CITY OF BLACKHAWK Denver, Colorado
U.S. DEPARTMENT OF THE INTERIOR BRUCE BABBITT, Secretary U.S. GEOLOGICAL SURVEY Charles G. Groat, Director The use of firm, trade, and brand names in this report is for identification purposes only and does not constitute endorsement by the U.S. Geological Survey. For additional information write to: Copies of this report can be purchased from: District Chief U.S. Geological Survey U.S. Geological Survey Information Services Box 25046, Mail Stop 415 Box 25286 Denver Federal Center Federal Center Denver, CO 80225-0046 Denver, CO 80225
CONTENTS Abstract Introduction Purpose and Scope Acknowledgments Location and Characteristics of Study Reaches Study Reach 1—Berthoud Falls to Golden Study Reach 2—Loveland Basin Ski Area to Georgetown Study Reach 3—Loveland Pass Study Reach 4—Berthoud Pass Determination of and Variation in Traveltime Rhodamine-WT Injection Procedures Rhodamine-WT Sampling Procedures Traveltime Data Analysis Variations in Traveltime in Mountain Streams Upper Clear Creek Traveltime Results and Discussion Study Reach 1—Berthoud Falls to Golden Study Reach 2—Loveland Basin Ski Area to Georgetown Study Reach 3—Loveland Pass Study Reach 4—Berthoud Pass Estimation of Upper Clear Creek Traveltimes Summary References FIGURES 1-3. Maps showing location of: 1. Upper Clear Creek Basin, Study Reaches 1 through 4, and injection and sampling sites for Study Reach 1—Berthoud Falls to Golden and for Study Reach 2—Loveland Basin Ski Area to Georgetown, Front Range 2. Study Reach 3—Loveland Pass and associated injection and sampling sites 3. Study Reach 4—Berthoud Pass and associated injection and sampling sites 4. Diagram showing dye-cloud dispersion and graph showing actual dye concentrations during highflow traveltime measurement, Berthoud Falls to Golden, June 11,1996 5-14. Graphs showing: 5. Rhodamine-WT concentration compared to time with curve fit of Gaussian and Lorentz distribution curves 6. Study Reach 1—Berthoud Falls to Golden traveltimes for three flow conditions 7. Study Reach 2—Loveland Basin Ski Area to Georgetown traveltimes for three flow conditions 8. Study Reach 3—Loveland Pass western tributary (subreach 3a) traveltimes for three flow conditions 9. Study Reach 3—Loveland Pass western tributary main-stem (subreach 3b) traveltimes for three flow conditions 10. Study Reach 3—Loveland Pass eastern tributary (subreach 3c) traveltimes for three flow conditions 11. Study Reach 4—Eastern Hoop Creek tributary (subreach 4a) traveltimes for three flow conditions 12. Study Reach 4—Western Hoop Creek tributary (subreach 4b) traveltimes for three flow conditions 13. Maximum, median, and minimum discharge at the Lawson gage for water years 1946 through 1986 and 1995 through 1997 and mean discharge during the three traveltime measurements 14. Relation between historical median discharges recorded at the Golden and the Lawson surfacewater gages CONTENTS
TABLES 1. Traffic accident and volume information for Study Reaches 1 and 2 2. Injection and sampling-site locations, site numbers, elevations, average slopes between sites, and discharge at the time of sampling 3. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 1—Berthoud Falls to Golden 4. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 2—Loveland Basin Ski Area to Georgetown 5. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 3—Loveland Pass 6. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 4—Berthoud Pass 7. Mean discharges recorded at Lawson gage during traveltime measurements 8. Estimates of leading-edge traveltime to Golden from various upstream sites over a range of Lawson gage discharges 9. Estimates of leading-edge traveltime to Silver Plume alluvial wells and Georgetown from various upstream sites over a range of Lawson gage discharges 10. Estimates of leading-edge traveltime to confluence with Clear Creek main channel from sites along U.S. Highway 6 on Loveland Pass over a range of Lawson gage discharges 11. Estimates of leading-edge traveltime to Hoop Creek confluence with West Fork of Clear Creek from sites along U.S. Highway 40 over a range of Lawson gage discharges CONVERSION FACTORS Multiply cubic foot (ft3) foot (ft) foot per second (ft/s) cubic foot per second (ft3/s) gallon (gal) mile (mi) mile per hour (mi/hr) square foot (ft2) By To obtain cubic meter meter meter per second cubic meter per second liter kilometer kilometer per hour square meter Degree Celsius (°C) may be converted to degree Fahrenheit (°F) by using the following equation: °F (1.8 x °C) + 32 National Geodetic Vertical Datum of 1929 (NGVD of 1929): A Geodetic datum derived from a general adjustment of the first-order level nets of both the United States and Canada, formerly called "Sea Level Datum of 1929." The following terms and abbreviations also are used in this report: greater than less than microgram per liter (µg/L) nanometer (nm) plus or minus (±) IV CONTENTS
Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97 By Sally M. Cuffin Abstract Increased traffic along mountainous stretches of Interstate Highway 70, U.S. High way 40, and U.S. Highway 6 in Colorado has resulted in a corresponding increase in the move ment of hazardous materials. The proximity of Clear Creek and its tributaries to these highways places downstream water users at risk in the event of an accidental hazardous-material release. A traveltime study was performed on two reaches of Clear Creek and two of its tributaries to provide the necessary information to allow downstream water managers to protect water supplies in the event of a hazardous-material release. The infor mation also can be used by hazardous-material response teams to intercept contaminants as they move downstream. This report summarizes the methods and findings of the traveltime study. Traveltime measurements were made using rhodamine-WT dye as a tracer in two reaches of Clear Creek and two Clear Creek tributaries in Clear Creek and Jefferson Counties, Colorado. The reaches were Clear Creek from the town of Berthoud Falls to the city limits of Golden; Clear Creek from the eastern edge of the Loveland Basin Ski Area parking lot to the town of Georgetown; the headwaters of two Clear Creek tributaries near Loveland Pass to the Loveland Valley Ski Area; and two unnamed trib utaries of Hoop Creek (a tributary of Clear Creek) near Berthoud Pass to the confluence with the West Fork of Clear Creek. Measurements were made at three times of the year to obtain data from different flow conditions. Traveltime and average velocities were determined for each stream reach. During high flow, dye-cloud leading-edge traveltimes ranged from about 0.6 hour along the Loveland Pass to the Loveland Valley Ski Area drainage to about 8.8 hours between Berthoud Falls and Golden. During low flow, leading-edge traveltimes ranged from about 2.6 hours along the same drainage from Loveland Pass to about 28.6 hours between Berthoud Falls and Golden. Average velocity between the Loveland Pass sites ranged from about 1.3 miles per hour during high flow to about 0.3 mile per hour during low flow. Average velocities between Berthoud Falls and Golden ranged from about 4.4 miles per hour during high flow to about 1.3 miles per hour during low flow. A curve-fitting program was used to fit Lorentz and Gaussian distributions to the data generated from the traveltime measurements. Because discrete (not continuous) traveltime measurements were made, an estimate of the actual time of the leading edge, peak, and trailing edge needed to be determined from the sample data. The curve-fitting program provided the means to calculate the timing of events (leading edge, peak, and trailing edge) that were not precisely measured. Calculated leading-edge, peak, and trailing-edge times were used to generate a series of graphs for each study reach. Traveltime estimation tables were generated from the data for a range of Clear Creek discharges. Because of the high variability of discharge within the basin, the Lawson Abstract
surface-water gage located near the center of the basin was used as the reference location. Discharge measurements for the Lawson gage are available on the Internet, which can be accessed by most hazardous-material-team dispatchers. Traveltimes determined during the individual studies were plotted against the corresponding discharge at the reference location. A curve-fitting program was used to generate a series of curves, which were used to produce traveltime estimation tables. INTRODUCTION In mountainous areas of Colorado, major high ways often follow stream valleys where grades are not so steep. The close proximity of streams and roads place these streams at risk of contamination in the event of a vehicular accident involving hazardous materials. Many of these "at risk" streams also supply water to downstream users. Population growth along the Front Range of Colorado and in nearby mountain communities has resulted in increased traffic along the mountain high ways and a corresponding increase in the movement of hazardous materials. In addition, mountain driving can be challenging because of winding roads and change able weather conditions. These factors can contribute to traffic accidents and possible associated hazardousmaterial spills. The population growth also is placing increasing demands on water supplies, and water suppliers need to be prepared if a stream becomes contaminated with hazardous materials. A water manager needs to know when to close intake valves to treatment plants and how long to keep them closed. Contaminants drawn through a water-treatment system can result in the potential distribution of contaminated water to the public and in the costly replacement of filters. A stream traveltime study can provide water suppliers and water managers with necessary informa tion in the event of a hazardous-material release. Soluble-tracer studies of streams can provide an effective and accurate method for the determination of traveltimes between a spill site and the intake for a domestic water supply or a temporary holding pond. In addition, the timing of the passage of the dye cloud provides useful information for determining the capacity of temporary holding ponds used to contain hazardous-material spills. Mountain stream characteristics are variable (slope; streambed materials, such as gravel, cobbles, and boulders; obstructions, such as fallen trees; and discharge), making traveltime estimations through a long mountainous stream reach difficult. Because Clear Creek is one of the "at risk" streams (fig. 1) in the Front Range of Colorado, the U.S. Geological Survey (USGS), in cooperation with the City of Blackhawk, began a study in 1996 to determine the traveltime for soluble contaminants between selected points along two reaches of Clear Creek and along two Clear Creek tributaries. The study stream reaches were: (1) The West Fork of Clear Creek from the town of Berthoud Falls to the Clear Creek confluence and continuing along Clear Creek to the city limits of Golden [potentially affected by spills from Interstate Highway 70 (I-70), U.S. Highway 40 (Hwy 40), and U.S. Highway 6 (Hwy 6)] (fig. 1); (2) the main channel of Clear Creek at the Loveland Basin Ski Area to the 6th Street bridge in Georgetown (potentially affected by spills from 1-70) (fig. 1); (3) two unnamed tributaries near Loveland Pass to the western edge of the Loveland Basin Ski Area parking lot (potentially affected by spills from Hwy 6) (fig. 2), and (4) two unnamed tribu taries flowing into Hoop Creek (a tributary of the West Fork of Clear Creek) near Berthoud Pass to the Hoop Creek crossing of Hwy 40 near its confluence with the West Fork of Clear Creek (potentially affected by spills from by Hwy 40) (fig. 3). The traveltime characteristics of the streams were measured using rhodamine-WT dye as a tracer. One objective for the study along the two Clear Creek tributaries was to provide information to the Colorado Department of Transportation for the design of detention ponds needed to capture hazardous-material spills prior to their introduction into the main stream channels. Traveltimes were determined at three times of the year during three different flow conditions: high flow (late spring); transitional flow (mid-summer); and low flow (early fall). Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
39°52'30" 105°52'30" 105°45' 105°37'30" 105°30' 105°22'30" Cree Grand I Junction C 0 L 0 R A D 0 LOCATION OF STUDY AREA a 105°15' J lt — tudy Reach 4 See fig. 3) A BGS1 s Golde '111G,S8 39°45' Cs7 N L) G or et wn GS4 -NA Gs LGS2"-- 1:111Y- „LpS3' , I Study Reach 3 E1,53ENHOWEP (See g. 2) re 47Ti 7I TUNg4- LGI1 I\, Loveland Ski Area ,98,10 ,660
0,
39°37'30" Base from Denver West 30 x 60 minute quadrangle 10 KILOMETERS 10 MILES STUDY REACH 1 EXPLANATION LGI1® INJECTION SITE—See table 2 for site number CONTOUR INTERVAL 820 FEET STUDY REACH 2 NATIONAL GEODETIC VERTICAL DATUM OF 1929 BGS6 SAMPLING SITE—See table 2 for HIGHWAY 40 SUBREACH site number INTERSTATE HIGHWAY 70 SUBREACH U.S. HIGHWAY 6 SUBREACH Figure 1. Location of Upper Clear Creek Basin, Study Reaches 1 through 4, and injection and sampling sites for Study Reach 1—Berthoud Falls to Golden and for Study Reach 2—Loveland Basin Ski Area to Georgetown, Front Range. INTRODUCTION 3
105°53'45" 105°52'30" 105°51'15" Dry
_11,600 39°41'15" Boundary of Loveland Basin Ski Area Boundary of
/- Loveland Valley Ski Area 12,200
(12,600 /Eisenhower
„MEMORIAL TUNNEL LPI3 39°40' ac NV / CO Base from Grays Peak and Loveland Pass 7.5 minute quadrangle 2 MILES 2 KILOMETERS CONTOUR INTERVAL 200 FEET NATIONAL GEODETIC VERTICAL DATUM OF 1929 EXPLANATION STUDY REACH 3 LPI3 ® INJECTION SITE—See table 2 for site number SUBREACH 3a LPS1a, SAMPLING SITE—See table 2 for SUBREACH 3b site number
SUBREACH 3c Figure 2. Location of Study Reach 3—Loveland Pass and associated injection and sampling sites. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
105°48'45" 105°47'30" 105°46'15: ib:70-0±-\/ C, 39°47'30" 11,800 39°46'1511 Base from Berthoud Pass 7.5 minute quadrangle 2 MILES 2 KILOMETERS CONTOUR INTERVAL 200 FEET NATIONAL GEODETIC VERTICAL DATUM OF 1929 EXPLANATION HU ammo' STUDY REACH 4 ® INJECTION SITE—See table 2 for site number SUBREACH 4a HS3SAMPLING SITE—See table 2 for SUBREACH 4b site number Figure 3. Location of Study Reach 4—Berthoud Pass and associated injection and sampling sites. Purpose and Scope were made on all study reaches, except Hoop Creek, during the high flow (mid-June 1996); the transiThis report presents the results of three sets of tional flow (mid-August 1996) when the stream traveltime data collected for two reaches of Clear Creek transitions from high to low flow; and the low flow and two of its tributaries. Traveltime measurements (early October 1996). The study was revised in INTRODUCTION 5
August of 1996 to include traveltime measurements for Hoop Creek during transitional flow and low flow of 1996 and high flow of 1997 (mid-June). Acknowledgments The author wishes to thank the members of the upper Clear Creek Watershed Association and the Colorado Department of Transportation for their assis tance with this study. Special thanks are extended to Robert Jones who negotiated steep mountain roads with the 2,500-gal fire tanker truck used to simulate spills for this study. Special thanks also are extended to Don Smith who provided access to the West Fork of Clear Creek at Berthoud Falls. The author also appre ciates the data-collection efforts of members of the Lakewood Field Office of the USGS. LOCATION AND CHARACTERISTICS OF STUDY REACHES Study Reach 1—Berthoud Falls to Golden Study Reach 1 extends from Berthoud Falls (elevation 9,800 ft) along the West Fork of Clear Creek to the western city limits of Golden (elevation 5,695 ft) along Clear Creek (fig. 1). The study reach was divided into three subreaches: the Hwy 40 subreach that includes the West Fork of Clear Creek from Berthoud Falls to the confluence with the main channel of Clear Creek (about 1.6 mi east of Empire, elevation 8,230 ft); the 1-70 subreach that includes the main channel of Clear Creek from the confluence with the West Fork of Clear Creek to the junction of 1-70 and Hwy 6 (about 4.5 mi east of Idaho Springs, elevation 7,210 ft); and the Hwy 6 subreach that includes the main channel of Clear Creek from the junction of 1-70 and Hwy 6 to the bottom of Clear Creek Canyon near the city limits of Golden (elevation 5,695 ft). The Hwy 40 subreach begins (injection site BGI1) in a primarily undeveloped, forested area and descends into areas of mountain communities and historical mining operations. The West Fork of Clear Creek parallels Hwy 40 from Berthoud Falls to its confluence with the main channel of Clear Creek. Distances between the stream and the highway through this subreach vary from several yards, about 1 mi east of Berthoud Falls, to about 0.25 mi, near Empire. The stream channel along the Hwy 40 subreach is characteristic of Colorado mountain streams, having streambeds consisting primarily of sands, gravels, cobbles, and boulders. Rock outcroppings and debris flows from steep mountain slopes have affected the stream channel along this subreach. The U.S. Fish and Wildlife Service has done extensive work along the western part of the Hwy 40 subreach to improve fish habitat by the use of small dams and rock struc tures. Because of limited anthropogenic effects in the western part of the subreach, the stream channel includes meanders, beaver ponds, channel vegetation (especially during high flow), and natural water falls. The stream channel was straightened along the eastern part of the Hwy 40 subreach to accommodate highway and residential construction and mining operations. The 1-70 subreach continues along the main channel of Clear Creek, paralleling 1-70 from the highway junction near Empire to the junction with Hwy 6, about 4.5 mi east of Idaho Springs. Elevations along this reach decrease from about 8,230 to about 7,210 ft. The stream borders the highway along about 90 percent of this subreach. Along the remaining 10 percent of the subreach, the stream borders frontage roads or residential and business development. Extensive straightening of the channel has occurred throughout the 1-70 subreach because of highway, business, and residential construction. The streambed throughout this subreach consists primarily of cobbles and boulders. The Hwy 6 subreach follows the main channel of Clear Creek through Clear Creek Canyon to Golden. The elevation decreases from about 7,210 ft at the junction of 1-70 and Hwy 6 to 5,695 ft at the city limits of Golden (sampling site BGS8). Clear Creek Canyon is a narrow canyon that has steep rock walls that limit development in the area. The highway is located within 50 to 100 ft of the stream throughout most of the canyon. The stream channel has been modified throughout much of this subreach to make room for the highway and mining operations. The streambed in the western part of the subreach consists primarily of cobbles and boulders. Channel vegetation affects stream velocities (primarily during high flow) in the eastern part of the subreach near Golden. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
A limited amount of traffic data is provided to indicate the trends since the early 1990's. Traffic acci dent and volume information for the highways along the study reach are provided in table 1 (Colorado Department of Transportation, written commun., 1997). The traffic data include the 1991 through 1996 period. An arbitrary comparison was made between the first 2 years and the last 2 years of the period. The 2-year period was chosen because of the limited data and to reduce the effect of an abnormal accident year (such as a year with a multi-car pileup). Study Reach 2—Loveland Basin Ski Area to Georgetown Study Reach 2 includes the reach of Clear Creek from the eastern edge of the Loveland Basin Ski Area parking lot (elevation about 10,840 ft) to Georgetown (elevation 8,512 ft) (fig. 1). Interstate 70 follows the valley carved by Clear Creek along this reach, and the distance from the highway to the creek varies from 50 ft to about 0.25 mi. Study Reach 2 begins at the Loveland Basin and Valley Ski Areas (injection site LGI1), passes through mostly undeveloped, forested land, and descends into areas of mountain communities and historical mining operations. The final sampling site is at the 6th Street bridge in Georgetown (LGS4). The western part of this reach passes through the Arapaho National Forest. Extensive work has been done to the Clear Creek stream channel by the U.S. Fish and Wildlife Service between the Loveland Basin Ski Area and Bakerville to improve fish habitat by the use of small dams and rock structures. Natural meanders, channel vegetation, and debris flows affect stream velocities in the western part of the reach. The 1-70 construction and historic mining operations have resulted in major disturbance of the stream channel, primarily in the eastern part of this reach, with large sections of the stream being straightened and rerouted. As in Study Reach 1, accidents and average daily traffic volume have increased along this stretch of highway (Colorado Department of Transportation, written commun., 1997) (table 1). Study Reach 3—Loveland Pass Study Reach 3 includes parts of two unnamed tributaries that flow into the main channel of Clear Creek near the western end of the Loveland Valley Ski Area parking lot (fig. 2). These tributaries drain the southern side of the Clear Creek Basin that is traversed by Hwy 6 through a series of steep grades and switch back curves. The tributaries are intersected by Hwy 6 several times as the highway winds up to the pass. The headwaters of the tributaries are located along the Table 1. Traffic accident and volume information for Study Reaches 1 and 2 (Colorado Department of Transportation, written commun., 1997) Stretch of highway Average number of accidents Percent increase Average daily traffic volume Percent increase Study Reach 1 U.S. Highway 40, Berthoud Falls 4,691 5,553 to Interstate 70 junction Interstate 70, junction 27,991 31,761 U.S. Highway 40 to junction U.S. Highway 6 (east of Idaho Springs) U.S. Highway 6, junction 7,178 12,058 Interstate 70 to Golden city limits Study Reach 2 Interstate Highway 70, 21,076 24,138 Eisenhower Memorial Tunnel to Georgetown 1Data not available for 1996; averse_puinber o OCATION AND CHARACTERISTICS OF STUDY REACHES
Continental Divide near Loveland Pass (elevation 11,992 ft). All of the study reach is located in the Arapaho National Forest. The study reach was divided into three subreaches to provide traveltime information from three potential accident sites. Subreach 3a follows an intermittent drainage to the confluence with a perennial Clear Creek tribu tary (flow is minimal during the winter) (fig. 2). Subreach 3a starts at the entrance of a culvert that passes under Hwy 6 about 0.6 mi from the top of Loveland Pass (injection site LPI1). The reach begins in alpine tundra and then rapidly descends through forested land to the main tributary at the bottom of the valley (passing again under Hwy 6 through another culvert). The drainage channel mostly consists of a series of small alternating waterfalls and pools. The water essentially steps down the mountainside until it reaches a grass and willows wetland at the bottom of the slope. There are numerous small channels mean dering through the wetland, but a large percentage of the water is absorbed and slowed by the vegetation. Once it reaches the main tributary, the water is again slowed by a meandering stream channel and extensive vegetation. The stream channel just upstream from the confluence with Clear Creek (sampling site LPS1) has been disturbed by activities at the Loveland Valley Ski Area. Subreach 3b is a reach of the same perennial Clear Creek tributary that drains subreach 3a (fig. 2). Subreach 3b begins at a culvert under Hwy 6 about 2.8 mi from the top of Loveland Pass (injection site LPI2). Subreach 3b starts in forested land about 0.6 mi upstream from the confluence with subreach 3a, meandering through the same grass and willows wetland. The upper part of this subreach has been disturbed by debris generated by a test bore for the Eisenhower Tunnel. Sampling site LPS1 was used for the subreach 3b traveltime measurement. Subreach 3c follows an intermittent drainage to the confluence with another perennial Clear Creek tributary (this tributary may completely freeze during some winters). Subreach 3c begins at a hairpin turn on Hwy 6, 1.2 mi from the top of Loveland Pass (injec tion site LPI3) (fig. 2). A small channel drains water that flows down the eastern side of the highway. The channel descends a steep mountainside to a valley containing the Clear Creek tributary and a Loveland Valley Ski Area chairlift. The subreach follows the valley passing through the Loveland Valley Ski Area parking lot (sampling site LPS2) to the confluence with Clear Creek. Although the area is primarily forest, some of the vegetation has been removed for the chairlift construction. Access roads and chairlift construction have disturbed parts of the stream channel for subreach 3c. Interstate 70 is the major east/west transporta tion corridor in Colorado and, as such, is a common route for transporting hazardous material. Trucks hauling such materials usually are not allowed through the Eisenhower Memorial Tunnel as a safety precau tion and normally are routed over Loveland Pass using Hwy 6. The Colorado Department of Transportation is exploring the possibility of locating a detention pond at the Loveland Valley Ski Area that would capture a hazardous-material release before the spill could reach the main stem of Clear Creek. Study Reach 4—Berthoud Pass Study Reach 4 includes two unnamed tributaries of Hoop Creek, a tributary of the West Fork of Clear Creek (fig. 3). Elevations in this study reach range from about 9,590 to 11,140 ft. The tributaries drain the northern side of the West Fork of Clear Creek Basin that is traversed by Hwy 40 through a series of steep grades and switchback curves. The headwaters for these tributaries are located along the Continental Divide near Berthoud Pass (elevation 11,315 ft). Study Reach 4 also is located in the Arapaho National Forest. All of the study reach is located in forested land. The study reach was divided into two subreaches to provide traveltime information from three potential accident sites. Subreach 4a begins at a culvert that passes under Hwy 40 (injection site HI1) about 0.6 mi from the top of Berthoud Pass (fig. 3), continues down stream to the confluence with Hoop Creek, and crosses under Hwy 40 just upstream from the confluence with the West Fork of Clear Creek (sampling site HS3). The subreach alternates between a series of small water falls and pools through forest and one small reach of meanders through a meadow. The lower part of the subreach follows the main channel of Hoop Creek, which becomes a braided channel as it passes through debris fields near the confluence with the West Fork of Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
Clear Creek. Stream channel disturbances along the subreach primarily are the present Hwy 40 roadbed and an older, abandoned roadbed. A major effect on subreach 4a is a diversion (Berthoud Pass ditch) that moves water from the northern side of the Continental Divide to the southern side, into Hoop Creek. The diversion generally begins flowing in late May or early June after snow has been cleared from the Hoop Creek channel. Flow continues through most of the summer until the water-rights allocations are satisfied. The gate to the diversion usually is shut sometime in late summer. Flows from the upper part of the subreach are decreased by about one-half when the gate is closed. Subreach 4b begins at a hairpin turn on Hwy 40 about 1.7 mi from the top of Berthoud Pass (fig. 3). Most of the subreach is a series of small waterfalls and pools until the confluence with Hoop Creek where the stream channel becomes braided. As with subreach 4a, the stream channel disturbances primarily are the present Hwy 40 roadbed and an older, abandoned roadbed. Debris flows from the Hwy 40 roadcuts also are affecting this subreach. DETERMINATION OF AND VARIATION IN TRAVELTIME The traveltime in the two reaches of Clear Creek and two of its tributaries was determined by injecting a fluorescent dye, rhodamine-WT and measuring the dye concentrations in samples collected at down stream sites (site locations and numbers provided in table 2). In traveltime studies, as the dye moves down stream, dispersion of the dye mass elongates and dilutes the dye cloud (fig. 4). At a nearby downstream site, water samples analyzed with a fluorometer will show a low concentration of dye in the leading edge of the cloud, a rapid rise in concentration to a peak value, and a slightly slower decline in concentration as the trailing edge of the cloud passes (fig. 4). Farther down stream, the time between the leading edge and peak concentration lengthens, with the arrival of the trailing edge (defined as 10 percent of the peak concentration for this study) stretching out considerably (fig. 4). Samples for this study were collected at selected intervals, usually 1 to 10 minutes, depending on flow conditions, at each site to determine the arrival of the leading edge, peak, and trailing edge of the dye cloud. The dye-concentration measurements were used to generate a set of curves, which can be used to estimate the arrival times for two reaches of Clear Creek and two of its tributaries. Average velocities between sampling sites were determined by dividing the distance between sites by the elapsed time for the dye-cloud leading edge to reach the downstream sampling site (these values are provided in the elapsed time tables for each study reach). Discharge and velocity were measured at several sampling sites for comparison to the average subreach velocity calculated by timing the dye cloud. Discharge was determined at the remaining sites from existing continuously recording surface-water gages or staff gages (table 2). A range of average velocities (from high to low flow) for each study reach was determined by dividing the total reach length by the elapsed time for the dye-cloud leading edge to reach the last sampling site (these values are provided in the text). Rhodamine-WT Injection Procedures A soluble dye injected into a stream assumes the flow characteristics of the water particles in that stream. Measuring the movement of the dye essen tially measures the movement of water particles and their dispersion characteristics (Kilpatrick and Wilson, 1989, p. 2). Rhodamine-WT is a highly soluble fluorescent dye with a specific gravity of 1.15 at 20°C. The stan dard form of rhodamine-WT used for traveltime studies is a 20-percent solution of the dye. Because the dye is very viscous (<25 centipoises at 25°C), slug-injection dye doses for this study were prepared by mixing a predetermined amount of dye into several gallons of water. The slug injection then could be made by rapidly pouring the mixed dye into the center of the stream, with a quick rinse of the container to remove the last of the rhodamine-WT. Without the initial dilution, several rinses of the container would be required, which would change the characteristics of what is intended to be a slug injection. The amount of dye used for each injection was determined using the equation described by Kilpatrick (1970). The relation between the quantity of dye required and the concentration expected at the end sampling site is as follows: DETERMINATION OF AND VARIATION IN TRAVELTIME 9
o Table 2. Injection and sampling-site locations, site numbers, elevations, average slopes between sites, and discharge at the time of sampling [ft, feet; ft/ft, feet per foot; ft3/s, cubic feet per second; mi, mile; --, no data; a, continuously recording surface-water gage; b, staff gage; c, stream-discharge measurement] Traveltimes AlongClear Creekand Selected Tributaries Upstream from Golden, Colorado,1996-97 Location Site number Distance upstream from last sampling (mi) site Elevation (ft) (eft) Average Average slope slope between over sites reach (ft/ft) Traveltime measurement discharge (ft3/s) High flow Transitional flow Low flow Discharge measurement obtained from Study Reach 1-Berthoud Falls to Golden (fig. 1) Berthoud Falls (injection site) BGI1 9,800 Berthoud Falls staff gage (0.7 mi east of Berthoud Falls) BGS1 9,690 b Hoop Creek confluence (1.4 mi east of Berthoud Falls) BGS2 9,600 West Fork of Clear Creek gage (1.2 mi east of Empire) BGS3 8,235 a Lawson gage (at Lawson) BGS4 8,080 1,010 a Idaho Springs 23d Street bridge BGS5 7,440 1,276 Clear Creek above Johnson Gulch (4.5 mi east of Idaho Springs) BGS6 7,210 1,330 a Junction of U.S. Highway 6 and State Highway 119 BGS7 6,910 Golden gage (100 ft downstream from U.S. Highway 6 bridge at west edge of Golden) BGS8 5,695 1,250 a Study Reach 2-Loveland Ski Area to Georgetown (fig. 1) Loveland Basin Ski Area (injection site) LGI1 10,840 Loveland Valley Ski Area gage (east end of Loveland Valley Ski Area) LGS1 10,615 a Bakerville staff gage (1-70 Bakerville exit) LGS2 9,710 b Downstream from Silver Plume alluvial wells (0.5 mi west of Silver Plume) LGS3 9,200 Georgetown 6th Street bridge LGS4 8,512 1Study Reach 3-Loveland Pass (fig. 2) Subreach 3a-western injection site (0.6 mi) LPI1 11,820 U.S. Highway 6 crossing downstream from injection site (2.1 mi) (injection site) LPI 1 a 11,380 Confluence with main stem of stream (0.2 mi below LPIla-not on road) LPSla 11,070 Upstream from west confluence with Clear Creek at Loveland Valley Ski Area LPS1 10,640 Subreach 3b-western tributary main-stem injection site (2.8 mi) LPI2 11,250 Upstream from west confluence with Clear Creek at Loveland Valley Ski Area LPS1 10,640 Subreach 3c-eastern injection site (1.2 mi) LPI3 11,620 Upstream from west confluence with Clear Creek at Loveland Valley Ski Area LPS2 10,640 2Study Reach 4-Berthoud Pass (fig. 3) Subreach 4a-eastern injection site (0.6 mi) HI1 11,140 Floral Park campground (2.7 mi) HS1 10,710 Eastern switchback downstream from Floral Park campground (3.8 mi) HS2 10,420 U.S. Highway 40 crossing upstream from confluence with West Fork of Clear Creek HS3 9,590 Subreach 4b-western injection site (1.7 mi) HI2 10,940 Western switchback upstream from Floral Park campground (3.5 mi) HS4 10,540 U.S. Highway 40 crossing upstream from confluence with West Fork of Clear Creek HS3 9,590 1Mileages refer to distance along U.S. Highway 6 from top of pass. 2A1l mileages refer to distance along U.S. Highway 40 from top of pass.
Dye cloud disperses Dye injection as it moves downstream Edges of dye cloud slowed by obstructions along streambanks Center of dye cloud travels with faster water near the top and center of the stream Note: Site numbers and locations provided in table 2.
a 2901 o g .1' ct 35 ;..0J) t o o o o J.J. 20 - c.) o o Trailing c.)4 Peak edge o 0 0 7r U E-4 o O Po n N o c5) o Leading a.)
O edge C4go P:1 O go O @ # Traveltime, in hours Figure 4. Diagram showing dye-cloud dispersion and graph showing actual dye concentrations during high-flow traveltime measurement, Berthoud Falls to Golden, June 11, 1996 (modified from Boyle and Spahr, 1985, fig. 3). Qm is the mean discharge of the reach (cubic
Vd 3.4 x 10 CP (1) feet per second); is the length of the reach (miles); is the mean stream velocity (feet per where second); and Vd is the volume of rhodamine-WT 20-percent is the peak concentration desired at the CP dye required (gallons); end of the reach (micrograms per liter). DETERMINATION OF AND VARIATION IN TRAVELTIME 11
Equation 1 is fairly easy to use in a reach of steadystate flow where discharge and velocity remain fairly constant; but the study reaches of Clear Creek start at high elevation, and the streams gain discharge and velocities vary as they descend the mountainous terrain. To properly use the equation, the mean velocity and corresponding mean discharge of the stream was estimated from historical records of several continuously recording surface-water gages. For Study Reaches 1 and 2, the rhodamine-WT dye was injected into the stream at night to best reflect the actual high flow for the stream. Clear Creek has a strong diel variation in flow during spring runoff (high flow) with the highest flows occurring near the top of the drainage shortly after dark. This water volume moves down the basin during the night, typically arriving near Golden at dawn. During high flow, the discharge at Golden can vary by as much as 200 ft3/s in 24 hours. Rhodamine-WT Sampling Procedures Rhodamine-WT is detected by a fluorometer that measures the luminescence of a fluorescent substance exposed to a light source of a given wavelength. Two Turner Designs Model 10 fluorome ters were used for this study. The higher the fluores cent dye concentration, the more light is emitted for the fluorometer to detect. The optimum excitation wavelength for rhodamine-WT is about 556 nm, with an optimum analyzing wavelength of about 580 nm. The sensitivity of a fluorometer allows rhodamine-WT dye to be detected to concentrations of less than 0.1 pg/L. A detailed discussion of the use of fluorome ters in dye tracing is in Wilson and others (1986). Grab samples were collected at selected time intervals from the streamflow center at each sampling site, using the sampling equipment described by Kilpatrick and Cobb (1985). Sample collection times were recorded for comparison to the injection time. A small amount of each sample was analyzed with an onsite fluorometer to determine the arrival of the leading edge, peak, and trailing edge of the dye cloud. Because fluorescence is temper ature sensitive, the remainder of the sample was taken to the USGS laboratory in Lakewood, Colorado, for analysis at a constant temperature. Samples were collected from the stream prior to the arrival of the dye cloud to determine any background fluorescence in the stream (Clear Creek background values varied from about 0.02 to 0.05 pg/L). Once the instream concentrations increased above the background levels, samples were kept for later analysis at the laboratory. Study Reach 1 had one injection and eight sampling sites; Study Reach 2 had one injection and four sampling sites; Study Reach 3 had four injection (includes one alternative site) and two sampling sites; and Study Reach 4 had two injection and four sampling sites (figs. 1-3 and table 2). Traveltime Data Analysis Analysis of the rhodamine-WT by the USGS laboratory provided a dye concentration for each sampled time. Because it is not possible to collect discrete samples at the exact time of the arrival of the leading edge, peak, or trailing edge of the dye cloud, an initial estimate of the time of these events was determined using graphical methods. To further refine the estimate of the arrival times, a curve-fitting program was used. A typical plot of the relation between time and dye concentration is shown in the graph in figure 4. The concentration values rise rapidly to the peak concentration and then trail off at a somewhat slower rate. The leading edge of the curve has the shape of a Gaussian distribution curve, but the trailing edge has a different distribution. A curve that fits the trailing-edge data best was a Lorentz distribution curve. To obtain the best mathematical representation of the data, the time/concentration curve was divided into two parts. Part one was the rise in concentration to the peak, and part two was the fall in concentration to the trailing edge (fig. 5). A curve-fitting program was used to fit each part of the curve (Gaussian distribution for part one and Lorentz distribution for part two) using a Monte Carlo algorithm. This process was repeated for each sampling site. Using the generated curves, arrival times of the leading edge, peak, and trailing edge of the dye cloud were calculated. The leading edge was defined as when the curve reached a value of 0.10 tg/L on the Gaussian distribution curve, the peak was the maximum value for the Gaussian curve, and the trailing edge was defined as 10 percent of the peak on the Lorentz curve. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
Elapsed time, in hours Figure 5. Rhodamine-WT concentration compared to time with curve fit of Gaussian and Lorentz distribution curves. Variations in Traveltime in Mountain Streams The hydrology of mountain streams is highly variable because of large changes in the topography of the stream channel and large fluctuations in stream discharge. Mountain stream discharge is affected by the weather-controlled release of water from mountain snowpacks and the yearly variation in the annual precipitation. One reason for measuring traveltimes at different times of the year was to determine the effect of some of these variations. A mountain stream can be thought of as a series of rough channels (sometimes steep) con necting a series of storage areas. Stream velocities and discharge along these streams are affected by a number of variables. Stream velocity in uniform channels can be described by the Manning equation, and the effect of storage areas on discharge can be described by a combination of the continuity equation and a storage function. Because mountain streams are not uniform, the Manning equation normally is not directly applicable, but equation variables describe the factors affecting stream velocities. The general form of the Manning equation is as follows: 2/3 1/2 V — R S (2) n where is the velocity of flow (feet per second); n is the Manning roughness coefficient; R is the hydraulic radius of the channel [the cross-sectional area of the channel, A (square feet), divided by the wetted perimeter of the channel cross section, P (feet)]; and S is the channel-bed slope (feet per feet) (Ward and Elliot, 1995, p. 212). DETERMINATION OF AND VARIATION IN TRAVELTIME 13
In mountain streams, the roughness coefficient can range from 0.030 in reaches that have gravels, cobbles, and a few boulders to 0.070 in reaches that have cobbles and large boulders (Ward and Elliot, 1995, p. 217). Factors affecting n include streambed material (earth, rock, and gravel); degree of irregu larity (smooth to severe); variations of channel cross section; relative effect of obstructions; vegetation; and degree of meandering (Ward and Elliot, 1995, p. 223). Channel-bed slopes (S) usually are larger in moun tainous areas because of elevation changes. Although only minimal changes occur in the slope over a year, the roughness of the channel can be affected by the stream expanding into the flood plains during high discharge. Large changes in discharge also affect the hydraulic radius (the daily mean flow at surface-water gaging station in Golden can vary from about 20 to about 2,300 ft3Is during the year). Streamflow through a storage location can be described by the continuity equation: dS — — (3) dt where dS is the change in storage (cubic feet), dt is the change in time (seconds),
is the input to the storage (cubic feet per second), and
is the output from the storage (cubic feet per second). The storage function dI d I dQ d Q S f (4) dt' dt2' dt ' dt2 provides the relation between S, I, and Q, contributing the information necessary to solve the continuity equa tion (Chow and others, 1988, p. 242-243). Storage areas usually slow stream velocity because of increases in the hydraulic radius of the stream and the time required to fill the storage (dt). In addition, when storage is increasing, the discharge out of the storage area usually is less than the discharge into the storage area — 0 if dSldt is positive], which can slow the output velocity if the channel areas upstream and downstream from the storage area are the same (Q vA). Large storage areas will affect traveltimes throughout the year, but the effect of small storage areas may only become apparent during low-flow conditions. Water rushing down a steep mountain slope often is perceived as fast moving. On closer examination, the stream channel is not continuous, but involves a series of steps and pools (channels and storage). The step-pool sequence observed along the steep mountain slopes are characteristic of headwater streams (Leopold, 1997, p. 67-68). Studies have indicated that the morphology of step-pool streams evolves toward a condition of maximum flow resistance. The step pools are a result of the material moved during the high-flow conditions to a position of maximum stability (Abrahams and Li, 1995, p. 2593). The maximum flow resistance developed in the step pools results in decreased velocities and increased traveltimes for the stream reach. To mathematically determine the stream velocity in a long mountain reach, a large number of stream subreaches would need to be characterized to estimate all of the necessary variables. The advantage of dye-tracer measurements becomes apparent when all of the variables affecting a mountain stream are considered. UPPER CLEAR CREEK TRAVELTIME RESULTS AND DISCUSSION Study Reach 1—Berthoud Falls to Golden The results of the three traveltime measure ments from Berthoud Falls to Golden are presented in table 3 and figure 6. Sampling-site locations and numbers are provided in table 2 and shown in figure 1. The measured traveltimes from the Berthoud Falls injection site (BGI1) to the various downstream sampling sites are listed in table 3. A graphical representation of the arrival of the dyecloud leading-edge, peak, and trailing-edge data for high, transitional, and low flow is shown in figure 6. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
Table 3. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 1-Berthoud Falls to Golden [Average velocity is determined by dividing reach length by traveltime between sites; measured velocity is the velocity determined by a discharge measurement at the site during traveltime sampling; no measurements were made at Hoop Creek during high flow of 1996; --, no data] UPPERCLEAR CREEK TRAVELTIME RESULTS AND DISCUSSION Sampling site Site number Distance upstream from Golden (miles) Arrival of leading edge (hours) (hours: minutes) Average velocity between sites (miles per hour) Measured stream velocity (miles per hour) Arrival of peak (hours) (hours: minutes) Average velocity between sites (miles per hour) Arrival of trailing edge (hours) (hours: minutes) Average velocity between sites (miles per hour) High-flow elapsed time and velocity Berthoud Falls (injection site) BGI1 00:00 00:00 00:00 Berthoud Falls staff gage BGS1 00:08 00:12 00:16 Hoop Creek confluence BGS2
West Fork of Clear Creek gage BGS3 02:24 02:45 03:15 Lawson gage BGS4 02:58 03:20 03:56 Idaho Springs 23d Street bridge BGS5 04:28 04:57 05:39 Clear Creek above Johnson Gulch BGS6 05:25 05:57 06:42 Junction Highways 6 and 119 BGS7 06:06 06:42 07:30 Golden gage BGS8 08:48 09:26 10:35 Transitional-flow elapsed time and velocity Berthoud Falls (injection site) BGI1 00:00 00:00 00:00 Berthoud Falls staff gage BGS1 00:26 00:36 00:47 Hoop Creek confluence BGS2 01:04 01:24 01:42 West Fork of Clear Creek gage BGS3 06:46 07:34 08:31 Lawson gage BGS4 08:16 09:04 10:10 Idaho Springs 23d Street bridge BGS5 12:15 13:10 14:39 Clear Creek above Johnson Gulch BGS6 14:38 15:32 17:13 Junction Highways 6 and 119 BGS7 16:18 17:27 19:05 Golden gage BGS8 23:16 24:33 26:46 Low-flow elapsed time and velocity Berthoud Falls (injection site) BGI1 00:00 00:00 00:00 Berthoud Falls staff gage BGS1 00:30 00:45 00:59 Hoop Creek confluence BGS2 01:20 01:51 02:23 West Fork of Clear Creek gage BGS3 08:53 09:53 11:17 Lawson gage BGS4 10:36 11:45 13:25 Idaho Springs 23d Street bridge BGS5 15:34 16:50 18:57 Clear Creek above Johnson Gulch BGS6 18:19 19:46 22:00 Junction Highways 6 and 119 BGS7 20:25 21:56 24:14 Golden gage BGS8 28:37 30:24 33:27
The arrival of the leading edge at Golden varied from about 8.8 hours during high flow to about 28.6 hours during low flow. During the high-flow measurement, the dye cloud required about 0.1 hour to pass the first sampling site (BGS1), but required about 1.8 hours to pass the Golden sampling site (BGS8). The dispersion increased during low flow as the dye cloud required about 0.5 hour to pass the first sampling site (BGS1) and about 4.8 hours to pass site BGS8. Average veloc ities between sampling sites are provided in table 3. The average velocity of the leading edge of the dye for this study reach was about 4.4 mi/hr during high flow and about 1.3 mi/hr during low flow. The precision of the traveltime measurements varied from about 1 minute for the samples collected at site BGS1 to between ±2 minutes (high flow) and ±10 minutes (low flow) at site BGS8. Although there are subtle changes in the gradient of the lines (fig. 6), the plots of the elapsed time, compared to the distance downstream, seem to be essentially linear from sampling site BGS5 (Idaho Springs) to BGS8 (Golden gage). The linear nature of this part of the plots indicates that the average veloci ties are relatively similar along this subreach of Study Reach 1. Average velocity data from table 3 indicates similar values along this subreach. The gradient of the plots change between each sampling site from BGS5 (Berthoud Falls staff gage) to BGS1, indicating more Note: Injection and sampling sites (such as BGI1 and BGS2) are described in table 2 and shown in figure 1; high-, transitional-, and low-flow values for the site are provided in 30 - table 2; x-axis for figure 6 increases from right to left. r- C.S z) cn ,,, 25 o cu' 7r E cn M ac1 cu cn 77) 15 ct
, G Distance up stre am from Golden gage, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW —13- Leading edge Leading edge ---E— Leading edge —e- Peak Peak —0-- Peak Trailing edge Trailing edge A Trailing edge Figure 6. Study Reach 1—Berthoud Falls to Golden traveltimes for three flow conditions. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
velocity variability in the upper part of the reach. The steeper the line (fig. 6), the slower the dye cloud passes through that subreach (lower velocity). Velocity variability is a function of the changes in discharge, channel characteristics, and storagearea effects. The data in table 2 indicate that the slope, S, along the upper subreaches [excluding the subreach between the injection point (BGI1) and the first sampling site (BGS1) that has minimal stream channel obstructions] of the study reach is steeper than in the lower subreaches, but the actual dye velocities were slower in the upper subreaches. If only the slope were used, the Manning equation (eq. 2) would predict faster velocities (the S value would be greater). Although changes in the Manning roughness coeffi cient can account for some of the velocity decreases, storage-area effects (eqs. 3 and 4) probably were the primary cause of the decreased velocity and longer traveltime. Storage areas along the upper reach of Study Reach 1 include numerous beaver ponds and small, low dams used to produce pooling for improved fish habitat. Study Reach 2—Loveland Basin Ski Area to Georgetown The results of the three traveltime measurements from Loveland Basin Ski Area to Georgetown are presented in table 4 and figure 7. Sampling-site loca tions and numbers are provided in table 2 and shown in figure 1. The arrival of the dye-cloud leading edge, peak, and trailing edge for the three flow conditions is shown in figure 7. The arrival of the leading edge in Georgetown varied from about 3.5 hours during high flow to about 15.7 hours during low flow. The dye cloud passed the first sampling site (LGS1) in about 0.2 hour and the last sampling site (LGS4) in about 1.1 hours during high flow. During low flow, the dye cloud required about 0.7 hour to pass LGS1 and about 6.0 hours to pass LGS4. The average velocity of the leading edge of the dye through Study Reach 2 was about 3.5 mi/hr during high flow and about 0.8 mi/hr during low flow (average velocities between sampling sites are provided in table 4). The slope is steeper in Study Reach 1 than in Study Reach 2, but discharge, channel characteristics, and storage-area effects combine to result in slower movement of the dye cloud through Study Reach 2 compared to Study Reach 1. The precision of the traveltime measurements varied from about ±1 minute for the samples collected at site LGS1 to between 2 minutes (high flow) and ±20 minutes (low flow) at site LGS4. The variability of the subreach characteristics in Study Reach 2 can be seen in the changes in the line gradients in figure 7. Although the plots of elapsed time compared to distance in figure 7 seem to be linear, closer examination shows distinct changes in gradient of the lines between sampling sites. The steeper the line, the slower the velocity and the longer the traveltime. In Study Reach 2, storage areas, meanders, and vegetation decrease stream velocities, but as discharge and slope increase, stream velocities increase. The largest change in average velocity between sites for Study Reach 2 occurred between the Silver Plume alluvial wells (LGS3) and Georgetown (LGS4) (table 4). This subreach includes an artificial widening of the stream, several abrupt changes in stream direction, and a series of waterfalls and pools. Study Reach 3—Loveland Pass The results of the three traveltime measure ments for the three subreaches in Study Reach 3 are presented in table 5 and figures 8 through 10. Sampling-site locations and numbers are provided in table 2 and shown in figure 2. The precision of the traveltime measurements varied from about 2 minutes for the samples collected at site LPS1 during high flow to between ±10 minutes (subreach 3b) and ±30 minutes (subreach 3a) during low flow. Traveltime-measurement precision at site LPS2 for subreach 3c varied from about ±1 minute during high flow to ±20 minutes during low flow. Because of the intermittent nature of flow in of subreaches 3a and 3c, the flow was supplemented with water from a fire tanker truck. Rhodamine-WT dye was added to 2,500 gal of water in the tanker. The tanker was driven to the two drainages, and about one-half of the tanker capacity was added to subreach 3a (LPI1) and the other one-half was added to subreach 3c (LPI3). The tanker provided the advan tage of simulating a hazardous-material spill. A slug injection was used in the large tributary (LPI2) because sufficient instream flow was available year round. UPPER CLEAR CREEK TRAVELTIME RESULTS AND DISCUSSION 17
Traveltimes Along Clear Creekand Selected Tributaries Upstream from Golden, Colorado,1996-97 tc, Table 4. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 2-Loveland Basin Ski Area to Georgetown [Average velocity is determined by dividing reach length by traveltime between sites; measured stream velocity is the velocity determined by a discharge measurement at the site during traveltime sampling; --, no data] Arrival of leading edge Average Arrival of peak Average Arrival of trailing edge Average Distance Measured velocity velocity velocity upstream stream Sampling Site between between between from (hours: velocity (hours: (hours: site number (hours) sites (hours) sites (hours) sites Georgetown minutes) (miles per minutes) minutes) (miles per (miles per (miles per (miles) hour) hour) hour) hour) High-flow elapsed time and velocity Loveland Basin Ski Area (injection site) LGI1 00:00 00:00 00:00 Loveland Valley Ski Area gage LGS1 00:16 00:21 00:26 Bakerville staff gage LGS2 01:47 02:00 02:22 Silver Plume alluvial wells LGS3 02:38 02:55 03:34 Georgetown 6th Street bridge LGS4 03:30 03:50 04:36 Transitional-flow elapsed time and velocity Loveland Basin Ski Area (injection site) LGI1 00:00 00:00 00:00 Loveland Valley Ski Area gage LGS1 00:59 01:13 01:27 Bakerville staff gage LGS2 06:01 06:35 07:35 Silver Plume alluvial wells LGS3 08:37 09:21 10:43 Georgetown 6th Street bridge LGS4 11:12 12:00 14:01 Low-flow elapsed time and velocity Loveland Basin Ski Area (injection site) LGI1 00:00 00:00 00:00 Loveland Valley Ski Area gage LGS1 01:18 01:39 02:01 Bakerville staff gage LGS2 08:30 09:24 11:47 Silver Plume alluvial wells LGS3 12:10 13:15 16:35 Georgetown 6th Street bridge LGS4 15:43 16:49 21:41
UPPERCLEAR CREEK TRAVELTIME RESULTS AND DISCUSSION Note: Injection and sampling sites (such as LGI1 and LGS1) are described in table 2 and shown in figure 1; high-, transitional-, and low-flow values are provided for this site in table 2; x-axis for figure 7 reads from right to left. cr) 7t20 ci) Distance upstream from Georgetown 6th Street bridge, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW Leading edge Leading edge —ii— Leading edge —,C3- Peak Peak —111— Peak —A- Trailing edge Trailing edge A Trailing edge Figure 7. Study Reach 2—Loveland Basin Ski Area to Georgetown traveltimes for three flow conditions.
Table 5. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 3-Loveland Pass [Average velocity is determined by dividing reach length by traveltime between sites; measured velocity is the velocity determined by a discharge measurement at the site during traveltime sampling; --, no data] Traveltimes Along Clear Creekand Selected TributariesUpstream from Golden, Colorado,1996-97 Sampling site Site number Distance upstream from final sampling site (miles) Arrival of leading edge (hours) (hours: minutes) Average velocity between sites (miles per hour) Measured stream velocity (miles per hour) Arrival of peak (hours) (hours: minutes) Average velocity between sites (miles per hour) Arrival of trailing edge (hours) (hours: minutes) Average velocity between sites (miles per hour) High-flow elapsed time and velocity Subreach 3a-western injection site LPI1 00:00 00:00 00:00 Highway 6 crossing below injection site LPIla Confluence with main stem of stream LPS la Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS1 00:58 01:13 01:51 Subreach 3b-main-stem (western) injection site LPI2 00:00 00:00 00:00 Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS1 00:43 00:49 00:57 Subreach 3c-eastern injection site LPI3 00:00 00:00 00:00 Above east confluence with Clear Creek main channel at Loveland Valley Ski Area LPS2 00:37 00:46 01:14 Transitional-flow elapsed time and velocity Subreach 3a-western injection site2 LPI1 00:00 00:00 00:00 Highway 6 crossing below injection site LPIla Confluence with main stem of stream LPSla Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS 1 03:00 04:00 06:15 Subreach 3b-main-stem (western) injection site LPI2 00:00 00:00 00:00 Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS 1 02:21 02:46 05:06 Subreach 3c-eastern injection site LPI3 00:00 00:00 00:00 Above east confluence with Clear Creek main channel at Loveland Valley Ski Area LPS2 01:37 02:03 04:14 Low-flow elapsed time and velocity Subreach 3a-western injection site3 LPI1 (3) (3) (3) Highway 6 crossing below injection site LPIla 00:00 00:00 00:00 Confluence with main stem of stream LPSla 00:53 01:10 01:49 Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS 1 03:05 03:37 06:27 Subreach 3b-main-stem (western) injection site LPI2 00:00 00:00 00:00 Above west confluence with Clear Creek main channel at Loveland Valley Ski Area LPS1 02:54 03:25 05:37 Subreach 3c-eastern injection site LPI3 00:00 00:00 00:00 Above east confluence with Clear Creek main channel at Loveland Valley Ski Area LPS2 02:36 03:21 12:18 1Subreach 3a and 3b final sampling site (LPS1) was located upstream from the western tributary confluence with the Clear Creek main channel. Subreach 3c final sampling site (LPS2) was located upstream from the eastern tributary confluence with the Clear Creek main channel. Both confluences were located along the western edge of the Loveland Valley Ski Area parking lot. 2Subreach 3a traveltime measurements estimated for transitional flow. Traveltimes affected by low flows in drainage. 3Subreach 3a traveltimes determined from injection site LPIla. Snow in drainage upstream from injection site LPIla absorbed 1,250 gallons of dye water from fire tanker truck.
UPPER CLEARCREEK TRAVELTIME RESULTS AND DISCUSSION Note: Injection and sampling sites (such as LPI1 and LPS1) are described in table 2 and shown in figure 2; high-, transitional-, and low-flow values are provided for this site in table 2; x-axis for figure 8 reads from right to left. v, 5.0 a. a.. ccs a I —A l'a1;
Distance upstream from Loveland Valley Ski Area parking lot near confluence with Clear Creek, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW —[3- Leading edge Leading edge —II— Leading edge - (3- Peak Peak
Peak —A- Trailing edge Trailing edge --A— Trailing edge Figure 8. Study Reach 3—Loveland Pass western tributary (subreach 3a) traveltimes for three flow conditions.
Traveltimes Along Clear Creekand Selected Tributaries Upstream from Golden, Colorado, 1996-97 Note: Injection and sampling sites (such as LPI2 and LPS1) are described in table 2 and shown in figure 2; high-, transitional-, and low-flow values are provided in table 2; x-axix for figure 9 reads from right to left. g 4.0 a a. E 3.0 "c) a.) eli ct 2.0 W , r MI 011 OF SS Distance upstream from Loveland Valley Ski Area parking lot near confluence with Clear Creek, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW —13- Leading edge Leading edge --111— Leading edge — 0- Peak Peak —0— Peak —A- Trailing edge Trailing edge —A— Trailing edge Figure 9. Study Reach 3—Loveland Pass western tributary main-stem (subreach 3b) traveltimes for three flow conditions.
UPPER CLEARCREEK TRAVELTIME RESULTS AND DISCUSSION Note: Injection and sampling sites (such as LPI3 and LPS2) are described in table 2 and shown in figure 2; high-, transitional-, and low-flow values for this site are provided in table 2; x-axis for figure 9 reads from right to left. -cs 6.0 a) Distance upstream from Loveland Valley Ski Area parking lot near confluence with Clear Creek, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW — El- Leading edge Leading edge —M— Leading edge — 0- Peak Peak —111— Peak — A- Trailing edge Trailing edge Trailing edge Figure 10. Study Reach 3—Loveland Pass eastern tributary (subreach 3c) traveltimes for three flow conditions.
The characteristics of each of the three subreaches affected the traveltime results. Traveltimes in subreach 3a had the greatest variability between flow regimes because of the intermittent nature of the drainage and complicating factors such as step pools, wetlands, amount of snow cover, and meanders. Subreaches 3b and 3c followed estab lished stream channels (the first 400 to 500 ft of the subreach 3c drainage was intermittent), decreasing variability in the traveltimes at different flow regimes. The hydrology of subreach 3a made it the most difficult among the subreaches to effectively measure traveltimes (fig. 8). During high flow, suffi cient water moved along the subbasin to carry the dye cloud through the step pools and wetlands. The leading edge of the dye cloud was easily detected at site LPS1 about 1.0 hour after it was injected at the top of the pass (table 5, fig. 8). By mid-summer (transi tional flow), most of the base flow was underground near the injection site and a barely detectable amount of dye managed to escape the step pools and wetlands. About 3.0 hours elapsed before the dye cloud was detected at site LPS1, and the concentrations never exceeded 0.20 [tg/L. Because of the low concentra tions, the actual arrival of the dye leading edge was hard to determine, but after the initial detection, dye was measured for at least 3.3 hours. Snow had fallen on the pass by the time of the low-flow measurement. After waiting more than an hour for the dye to travel 0.2 mi, it was determined that the entire 1,250 gal injected by the tanker truck had been absorbed by the new snow in the drainage. To complete the measure ment, a slug of dye was injected at the highway crossing (LPI1a). About 3.1 hours had elapsed as the dye-cloud leading edge passed through the shortened route (table 5). Dispersion for subreach 3a can be determined from the traveltimes provided in table 5, but previously mentioned characteristics (intermittent flow and snow cover in the drainage) in this subreach limit the accuracy of dispersion calculations. Subreach 3b follows a perennial stream to the confluence with the main stem of Clear Creek. The leading edge of the dye cloud arrived at the subreach 3b sampling site (LPS1) in about 0.7 hour during high flow and about 2.9 hours during low flow (table 5, fig. 9). The effect of discharge on dispersion in subreach 3b is evident in the time required for the dye cloud to pass the sampling site. In subreach 3b, the time required for the dye cloud to pass site LPS1 varied from about 0.2 hour during high flow to about 2.7 hours during low flow. The arrival of the leading edge of the dye cloud in subreach 3c was not affected significantly by the intermittent nature of the start of the subreach. The leading edge of the dye cloud arrived at the subreach 3c sampling site (LPS2) in about 0.6 hour during high flow and about 2.6 hours during low flow (table 5, fig. 10). The effect of discharge on dispersion was more significant in subreach 3c than in subreach 3b. In subreach 3c, the time required for the dye cloud to pass site LPS2 varied from about 0.6 hour during high flow to about 9.7 hours during low flow. Factors that affected dispersion in subreach 3c included the use of the fire tanker truck (it required about 3 minutes to empty the 1,250 gal of dyed water) and the number of step pools. The high-flow leading-edge average velocities for the subreaches are as follows: subreach 3a, about 1.3 mi/hr; subreach 3b, about 1.8 mi/hr; and subreach 3c, about 1.3 mi/hr. The gradients of the lines plotted in figures 8 through 10 (and the data in table 5) indicate slower velocities than the velocities deter mined in Study Reaches 1 and 2. Slopes (S) in Study Reach 3 are almost an order of magnitude greater than slopes in Study Reaches 1 and 2 (table 2). The major characteristics affecting stream velocities in Study Reach 3 seem to be small discharge volumes, mean ders, wetlands, snow cover, and step pools, but not the slope. Study Reach 4—Berthoud Pass The results of the three traveltime measure ments for the two subreaches in Study Reach 4 are presented in table 6 and figures 11 and 12. Samplingsite locations and numbers are provided in table 2 and shown in figure 3. The precision of the traveltime measurements varied from about 1 minute for the samples collected at HS3 during high flow to between ±10 minutes (subreach 4b) and ±20 minutes (subreach 4a) during low flow. Because Study Reach 4 was added to the overall study after the initial highflow measurements, an additional traveltime measure ment was conducted in late spring 1997 to quantify the high-flow conditions. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
Table 6. Elapsed time between injection and arrival of dye at sampling sites and average velocity between sites for Study Reach 4-Berthoud Pass [Average velocity is determined by dividing reach length by traveltime between sites; measured velocity is the velocity determined by a discharge measurement at the site during traveltime sampling; UPPER CLEARCREEK TRAVELTIME RESULTS AND DISCUSSION --, no data] Sampling site Site number Distance upstream from final sampling site (miles) Arrival of leading edge (hours) (hours: minutes) Average velocity between sites (miles per hour) Measured stream velocity (miles per hour) Arrival of peak (hours) (hours: minutes) Average velocity between sites (miles per hour) Arrival of trailing edge (hours) (hours: minutes) Average velocity between sites (miles per hour) High-flow elapsed time and velocity Subreach 4a-eastern injection site HI1 00:00 00:00 00:00 Floral Park campground HS1 00:13 00:19 00:24 Eastern switchback below Floral Park HS2 00:27 00:34 00:39 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 00:45 00:54 01:01 Subreach 4b-western injection site H12 00:00 00:00 00:00 Western switchback below Floral Park HS4 00:17 00:25 00:31 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 00:40 00:48 00:55 Transitional-flow elapsed time and velocity Subreach 4a-eastern injection site HI1 00:00 00:00 00:00 Floral Park campground HS1 01:01 01:21 02:01 Eastern switchback below Floral Park HS2 02:01 02:10 03:09 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 02:54 03:16 05:28 Subreach 4b-western injection site 00:00 00:00 00:00 Western switchback below Floral Park HS4 00:45 00:58 01:10 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 01:50 02:08 02:36 Low-flow elapsed time and velocity Subreach 4a-eastern injection site HI1 00:00 00:00 00:00 Floral Park campground HS1 01:24 01:52 02:50 Eastern switchback below Floral Park HS2 03:05 03:40 05:57 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 04:57 05:44 12:30 Subreach 4b-western injection site H12 00:00 00:00 00:00 Western switchback below Floral Park 1-1S4 01:08 01:26 01:49 Highway 40 crossing above confluence with West Fork of Clear Creek HS3 02:48 03:24 04:37 1Sampling site (HS3) was located at the Hoop Creek Highway 40 crossing upstream from the confluence with the West Fork of Clear Creek. cri"
" cn Traveltimes Along Clear Creekand Selected TributariesUpstream from Golden, Colorado, 1996-97 Note: Injection and sampling sites (such as HI1 and HS2) are described in table 2 and shown in figure 3; high-, transitional-, and low-flow values for this site are provided in table 2; x-axis for figure 11 reads from right to left. ,,, 10.0 o Cr) -5-, 8.0 CID
E 7, 6.0 I) a c'z w 4.0 Emmi MM. Distance upstream from U.S. Highway 40 crossing of Hoop Creek near confluence with West Fork of Clear Creek, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW Leading edge Leading edge Leading edge — 0- Peak Peak --111— Peak — A— Trailing edge Trailing edge —A-- Trailing edge Figure 11. Study Reach 4—Eastern Hoop Creek tributary (subreach 4a) traveltimes for three flow conditions.
UPPER CLEAR CREEK TRAVELTIME RESULTS AND DISCUSSION Note: Injection and sampling sites (such as HI2 and HS3) are described in table 2 and shown in figure 3; high-, transitional-, and low-flow values for this site are provided in table 2; x-axis for figure 12 reads from right to left. m cA (4'w 3.5 o
a;E 2.5
2.0 ct , ' " .1.1.
, mom. mom. ' m ,
, , Distance upstream from U.S. Highway 40 crossing of Hoop Creek near confluence with West Fork of Clear Creek, in stream miles EXPLANATION HIGH FLOW TRANSITIONAL FLOW LOW FLOW —1± Leading edge Leading edge Leading edge —o- Peak Peak —II-- Peak —A- Trailing edge Trailing edge --A Trailing edge Figure 12. Study Reach 4—Western Hoop Creek tributary (subreach 4b) traveltimes for three flow conditions.
Leading-edge traveltimes for subreach 4a at site HS3 ranged from about 0.8 hour for high flow to about 5.0 hours during low flow (table 6, fig. 11) When the upstream diversion gate is closed, the upper reach of subreach 4a loses about one-half its discharge, and traveltimes are increased. The diversion was flowing during the high- and transitional-flow measurements, but not during the low-flow measure ment. The dye cloud passed sampling site HS3 in about 0.3 hour during high flow, but required about 7.6 hours to pass during low flow. Step pools were the primary dispersion mechanism as the dye cloud moved down the drainage. Average velocities for the leading edge of the dye cloud for subreach 4a varied from about 2.1 mi/hr during high flow to about 0.3 mi/hr during low flow. In subreach 4b, leading-edge traveltimes at site HS3 ranged from about 0.7 hours during high flow to about 2.8 hours during low flow (table 6, fig. 12). The dye cloud passed sampling site HS3 in about 0.3 hour during high flow and in about 1.8 hours during low flow. Average velocities for the leading edge of the dye cloud were about 1.8 mi/hr during high flow and about 0.4 mi/hr during low flow. Although subreach 4a is longer (1.6 mi for subreach 4a and 1.2 mi for subreach 4b), the effect of the upstream diversion on subreach 4a is evident in the variability between low- and high-flow measure ments for the two subreaches. Additional factors that affected the subreach 4a traveltime include meanders, step pools, and vegetation along the streambank. As with Study Reach 3, the gradients of the lines plotted in figures 11 and 12 (and the data in table 6) indicate slower velocities than velocities in Study Reaches 1 and 2. Mountain slopes in Study Reach 4 are about an order of magnitude steeper than slopes in Study Reaches 1 and 2 (table 2), but the primary factors affecting stream velocity through these subreaches include the step pools and the vari able discharge. ESTIMATION OF UPPER CLEAR CREEK TRAVELTIMES The transferability of traveltime measurement data from this study are limited because the elapsed times are best used for the discharges occurring in Clear Creek during the time of the study measure ments. A method was needed to estimate traveltimes for other discharges. It is desirable to be able to relate elapsed traveltime to discharge. Because most emergency responders do not arrive at the scene with a method of determining stream discharge, access to current discharge data is needed. Real-time information from two stream gages in the Clear Creek Basin is available on the Internet (http://nwis-colo.cr.usgs.gov/rt-cgi/gen_tbl_pg), and this information can be accessed by most emergency dispatchers. One gage is located at the city limits of Golden, and another is located near Lawson. The Golden gage is affected by diversions for the Golden water-treatment plant, the Welch ditch, and the Church ditch. The Lawson gage is located near the center of the basin and has no major diversions upstream from it. Forty-four years of discharge data are available for the Lawson gage, which are shown in figure 13. The mean discharges (and variation) that occurred during the three traveltime measurements also are shown in figure 13. The mean discharges recorded at the Lawson gage during the traveltime measurements at the four study reaches and the amount of discharge variation during each sampling period are provided in table 7. To provide estimates of traveltime for discharges other than the discharges existing at the time of the study, leading-edge elapsed time compared to the Lawson discharge was plotted. A curve-fitting program was used to achieve the best fit of the data. A power curve fit of the following form was selected: b y ax (5) where a and b are constants determined by the curvefitting program, is the discharge, and y is the elapsed time. Leading-edge data from high, transitional, and low flows were used to develop a set of curves for each sampling site in Study Reaches 1 through 4, and these curves were used to generate estimated traveltimes for discharges other than discharges that occurred during the study (tables 8-11). Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
1,800 1,600 -c) c.) 1,400 ct) Q. 1'200 alL U
c.) an 600 c.)c.) 400 Median — — - Minimum — — Maximum Mean flow during traveltime measurement z + 2 standard deviations oft— Mean - 2 standard deviations Note: A water year is the 12-month period, October 1 through September 30. The water year is designated by the calendar year in which it ends. r ri
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Figure 13. Maximum, median, and minimum discharge at the Lawson gage for water years 1946 through 1986 and 1995 through 1997 and mean discharge during the three traveltime measurements. Table 7. Mean discharges recorded at Lawson gage during traveltime measurements [Discharge measured in cubic feet per second] Traveltime measurement Berthoud Falls to Golden gage (fig. 1) Loveland Basin Ski Area to Georgetown (fig. 1) Loveland Pass vicinity to Loveland Valley Ski Area (fig. 2) Hoop Creek tributaries to confluence with West Clear Creek (fig. 3) Flow conditions High-1996 Transitional-1996 Low-1996 High-1996 Transitional-1996 Low-1996 High-1996 Transitional-1996 Low-1996 High-1996 Transitional-1996 Low-1997 Date of dye injection 06/11/96 08/13/96 09/30/96 06/10/96 08/14/96 10/01/96 06/14/96 08/15/96 10/01/96 08/15/96 10/01/96 06/18/96 Mean discharge at Lawson gage during traveltime measurement (±2 standard 977±65 134±6 82±8 987±24 131±6 78±1 923±33 128±7 78±1 126±4 80±5 875±3 1Mean and standard deviation values were determined from the discharge values recorded (discharge recorded every 15 minutes) at the Lawson gage over the sampling period (time from injection until passage of trailing edge at final sampling site). ESTIMATION OF UPPER CLEAR CREEK TRAVELTIMES 29
Traveltimes Along Clear CreekandSelected Tributaries Upstream from Golden, Colorado, 1996-97 Table 8. Estimates of leading-edge traveltime to Golden from various upstream sites over a range of Lawson gage discharges [Data in this table are subject to the limitations discussed in the "Estimation of Upper Clear Creek Traveltimes" section of the report; sampling sites shown in fig. 1 and described in table 2; ft3/s, cubic feet per second; hr, hours; min, minutes] Sampling site Discharge at Lawson gage (ft3/s) Berthoud Falls (BGI1) Berthoud Falls gage (BGS1) Hoop Creek confluence (BGS2) West Fork of Clear Creek gage (BGS3) Lawson gage (BGS4) Idaho Springs 23d Street bridge (BGS5) Clear Creek above Johnson Gulch gage (BGS6) Junction Highways 6 and 119 (BGS7) hr min hr min hr min hr min hr min hr min hr min hr min 1,000 1,050 1,100 1,150 1,200 1,250 1,300 1,350 1,400 1,450
Table 9. Estimates of leading-edge traveltime to Silver Plume alluvial wells and Georgetown from various upstream sites over a range of Lawson gage discharges [Data in this table are subject to the limitations discussed in the "Estimation of Upper Clear Creek Traveltimes" section of the report; site locations shown in fig. 1 and described in table 2; ft3/s, cubic feet ESTIMATION OF UPPER CLEAR CREEK TRAVELTIMES per second; hr, hours; min, minutes] Traveltime to Silver Plume infiltration wells from: Traveltime to Georgetown from: Discharge at Lawson gage (ft3/s) Loveland Basin Ski Area (LGI1) Sampling sites Loveland Valley Ski Area gage (LGS1) Bakerville staff gage (LGS2) Loveland Basin Ski Area (LGI1) Sampling sites Loveland Valley Ski Area gage (LGS1) Bakerville staff gage (LGS2) Silver Plume infiltration wells (LGS3) hr min hr min hr min hr min hr min hr min hr min 1,000 1,050 1,100 1,150 1,200 1,250 1,300 1,350 1,400 1,450
Table 10. Estimates of leading-edge traveltime to confluence with Clear Creek main channel from sites along U.S. Highway 6 on Loveland Pass over a range of Lawson gage discharges [Data in this table are subject to the limitations discussed in the "Estimation of Upper Clear Creek Traveltimes" section of the report; site locations shown in fig. 2 and described in table 2; ft3/s, cubic feet per second] Sampling sites Discharge at Lawson gage (ft3/s) West injection site (LPI1) Main-stem injection site (LPI2) East injection site (LPI3) hour minute hour minute hour minute 1,000 1,050 1,100 1,150 1,200 1,250 1,300 1,350 1,400 1,450 Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
Table 11. Estimates of leading-edge traveltime to Hoop Creek confluence with West Fork of Clear Creek from sites along U.S. Highway 40 over a range of Lawson gage discharges [Data in this table are subject to the limitations discussed in the "Estimation of Upper Clear Creek Traveltimes" section of the report; sampling sites shown in fig. 3 and described in table 2; ft3/s, cubic feet per second] Sampling sites Discharge at Lawson gage (ft3/s) East injection site (HI1) Floral Park campground (HS1) East switchback (HS2) West injection site (HI2) West switchback (HS4) hour minute hour minute hour minute hour minute hour minute 1,000 1,050 1,100 1,150 1,200 1,250 1,300 1,350 1,400 1,450 ESTIMATION OF UPPER CLEAR CREEK TRAVELTIMES 33
Because the data set for each sampling site consisted of only three data points, these fitted curve estimates need to be used with care. Although the traveltime estimation within the range of the Lawson discharges (about 80 to 990 ft3/s) may be relatively accurate, large deviations could occur for discharges greater than and less than this range. The correlation coefficients (r2) ranged from 0.95 to 0.99, but this range would be expected for a three data-point curve fit. The actual variation of the data between the three points may be large, introducing error into the elapsed time calculated for a specific discharge. Users need to allow a safety factor when using these tables and need to assume the leading edge can arrive sooner than the tables estimate. In addition to the uncertainty of the curve fit, errors were introduced into the estimations because of conditions occurring during the actual traveltime data measurements. A heavy rainstorm occurred late in the afternoon during the low-flow sampling at Study Reach 3. Stream discharge probably increased during this time, but the procedure used to generate the estimation tables assumed a constant discharge. Traveltimes estimated for the low-flow periods in Study Reach 3 probably are conservative because the estimation curve was based on lower flows (table 10). The diversion was closed during the lowflow traveltime measurements in Study Reach 4, which again may have introduced error into the esti mates (table 11). For the low-flow periods when the diversion remains open, the estimated traveltimes are underestimated (that is, the contamination would move faster). Localized precipitation in one or more subbasins can have major effects on discharge in other parts of the Clear Creek Basin. For example, a heavy summer rainstorm in the Chicago Creek Basin (fig. 1) could decrease the amount of traveltime between Idaho Springs and Golden, and the gage at Lawson would record nothing unusual. The relation between median discharge recorded at the Golden and Lawson surface-water gages is shown in figure 14. Large varia tions from this relation could indicate flooding in the lower basin, but the graph shows variations of more than ±100 ft3/s, making it difficult to determine 700 It 600 Equation of line: y 0.789*x - 4.645 R2 0.98 a.) S4 zc.) 400 tit) C.) cA O 1,000 Golden discharge, in cubic feet per second Figure 14. Relation between historical median discharges recorded at the Golden and the Lawson surface-water gages. Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97
if diversions, flooding, or surface-water-gage error is involved. An alternative would be to check weather conditions along with the Lawson discharge. The estimation tables were not designed to be used during times of flooding. If flooding does occur in the lower basin, a conservative safety factor needs to be applied to the estimated traveltimes (about 1 to 2 hours during high flow and 2 or more hours during low flow) to ensure the leading edge of a plume will be contained. Several additional factors can affect traveltime to downstream locations. Diversions upstream from Golden can affect traveltimes, as can reservoirs, such as Georgetown Lake. Also, the type of hazardous material spilled needs to be noted. Rhodamine-WT dye is very water soluble, whereas gasoline is not. A soluble chemical behaves similarly to the rhodamine-WT, but organic chemicals that have low solubility cling to surfaces, potentially leaching into the stream for an extended period of time. The leading edge may arrive at about the same time as the rhodamine-WT, but the trailing edge can be extended. Another factor is that the rhodamine-WT dye was injected as a slug. An actual spill may leak contamination into the stream for a number of hours, again lengthening the trailing edge. SUMMARY Population growth in the mountainous areas along the Colorado Front Range has resulted in increased traffic and a corresponding potential increase for accidents, possibly involving hazardousmaterial carriers. Because of the proximity of moun tain streams to highways, hazardous-material spills can affect downstream water supplies. This study determined traveltimes along four reaches of the upper Clear Creek Basin to provide downstream water managers and hazardous-material-response teams with a method of estimating the arrival times of hazardousmaterial spills. Traveltime studies are a useful tool that help to minimize the effect of hazardous-material spills into streams that are used for water supply. The complex nature of mountain streams affects many estimation techniques and requires actual measurements to deter mine the actual traveltimes. Channel characteristics in the upper Clear Creek Basin vary from intermittent rills flowing from snow fields to artificially straightened channels contained by steep canyon walls. Dyetracer (rhodamine-WT) measurements provide useful information from such areas. Traveltime measurements were made at three times of the year to obtain data during three different flow conditions. Leading-edge traveltimes along the study reaches varied between high and low flow as follows: about 8.8 to about 28.6 hours between Berthoud Falls and Golden (average velocity varied from about 4.4 to about 1.3 mi/hr); about 3.5 to about 15.7 hours between the Loveland Basin Ski Area and Georgetown (average velocity varied from about 3.5 to about 0.8 mi/hr); about 0.7 to about 2.9 hours between the Loveland Pass subreach 3b injection site (LPI2) and sampling site (LPS1) (average velocity varied from about 1.8 to about 0.4 mi/hr); and about 0.8 to about 5.0 hours between Berthoud Pass subreach 4a injection site (HI1) and sampling site (HS3) (average velocity varied from about 2.1 to about 0.3 mi/hr). The study indicated the great variability of a mountainous system where leading-edge traveltimes could be three to six times longer at low flow than at high flow. Factors such as beaver ponds, waterfalls, and manmade structures for fish habitat improvement can substantially affect the time required for a dye cloud to pass through a stream reach. The step-pool characteristic of high mountain streams proved to be a major factor in average reach velocity in the headwater streams. Snow fields near the Continental Divide seemed to be effective, temporary spill-containment systems. The variable nature of Clear Creek and its tribu taries can cause problems when making estimations from the data. Measurements during three discharge conditions provided sufficient data to develop a rela tion between discharge and the time required for the leading edge of a contaminant plume to arrive at a downstream site. The validity of the estimated traveltimes for discharges greater than or less than the discharges measured during the study was not deter mined. Estimated traveltimes always need to be used with care until additional data can verify the estima tion. Factors that did not occur during the study, such as intense rainfalls in one or two subbasins, need to be considered when using the estimated traveltime tables. The estimated traveltimes need to be used as guide lines, not as absolute values. SUMMARY 35
REFERENCES Abrahams, A.D., and Li, Gang, 1995, Step-pool streams—Adjustments to maximum flow resis tance: Water Resources Research, v. 31, no. 10, p. 2593-2602. Boyle, J.E., and Spahr, N.E., 1985, Traveltime, longitudinal-dispersion, reaeration, and basin characteristics of the White River, Colorado and Utah: U.S. Geological Survey Water-Resources Investigations Report 85-4050, 54 p. Chow, V.T., Maidment, D.R., and Mays, L.W., 1988, Applied hydrology: New York, McGraw-Hill, 572 p. Kilpatrick, F.A., 1970, Dosage requirements for slug injec tions of rhodamine BA and WT dyes, in Geological Survey Research 1970: U.S. Geological Survey Profes sional Paper 700—B, p. 250-253. Kilpatrick, F.A., and Cobb, E.D., 1985, Measurement of discharge using tracers: U.S. Geological Survey Tech niques of Water-Resources Investigations, book 3, chap. A16, 52 p. Kilpatrick, F.A., and Wilson, J.F., Jr., 1989, Measurement of time of travel in streams by dye tracing: U.S. Geolog ical Survey Techniques of Water-Resources Investiga tions, book 3, chap. A9, 27 p. Leopold, L.B., 1997, Water, rivers and creeks: Sausalito, Calif., University Science Books, 185 p. Ward, A.D., and Elliot, W.J., 1995, Environmental hydrology: New York, CRC Press, Inc., 462 p. Wilson, J.R., Jr., Cobb, E.D., and Kilpatrick, F.A., 1986, Fluorometric procedures for dye-tracing: U.S. Geolog ical Survey Techniques of Water-Resources Investiga tions, book 3, chap. Al2, 41 p. (Revised). Traveltimes Along Clear Creek and Selected Tributaries Upstream from Golden, Colorado, 1996-97 U.S. GOVERNMENT PRINTING OFFICE: 1999-773-084 / 20052 Region No. 8
Cuffin-TRAVELTIMES ALONG CLEAR CREEK AND SELECTED TRIBUTARIES UPSTREAM FROM GOLDEN, COLORADO, 1996-97 USGS/WRIR 98-4151